Churchill House, St Albans

Project Gallery

Client: F&C REIT Asset Management

Value: £2,050,000

Contract: Design and Build

Project Manager: Madlin + Maddison

Architect: Buckley Gray Yeoman

Quantity Surveyor: Madlin + Maddison

Structural Engineer: Chamberlain Consulting

M&E Consultant: ITD

This negotiated project was the Cat A fit-out of an existing 20,000ft² office building with a fast-track 25 week programme. The project had the added complexity of an incumbent tenant who was relocated to the second floor whilst the first floor was refurbished then back to first floor once the fit-out works had been sufficiently progressed.

The scope of works included stripping out the existing M&E services, suspended ceilings, toilet cores and reception curtain walling. A new VRV heating
system, electrical installations and security systems were installed, along with reconfigured toilet cores and communal areas. The reception was completely
remodelled, with the double height glazing panels in brick reveals upgraded with a complete structural glass solution.